Richmond Drainage Improvements: Final Push (story continued)

Richmond Construction

Asphalt work on Richmond is now complete leaving only minor curb and ramp work, permanent lane striping and back-of-curb sodding and restoration to complete the project. This will likely be done next week approximately 40-days ahead of the contract schedule. 

Read more...

Richmond Drainage Improvements: Final Push

Richmond Construction

Richmond construction is nearly complete. Final asphalt activity will account for the majority of the work next week along with lane striping and general project area restoration. 

Read more...

Richmond Drainage Improvements: Westbound Restoration to be Completed Today

Richmond Construction

The westbound lanes on Richmond Avenue are likely to be asphalted in their entirety later today leaving only minor work prior to substantial completion of the project.

Read more...

Richmond Drainage Improvements: Main Lane Asphalt Complete

Richmond Construction

The northern half of Richmond is now complete with asphalt and open to full access. Over the next week, crews will work to restore impacted sections on the south side of the street as well as some left-turn bays. Final striping also remains to be completed.

Read more...

Richmond Drainage Improvements: Asphalt to Begin Next Week

Richmond Construction

Concrete work this week went extremely well and will continue into next week. Paving activity on the eastbound lanes at Lake, Audley and Eastside and the westbound lanes at Virginia have made great progress.