Upper Kirby Construction: Work Continues Between Argonne and Dickey

Westheimer Paving, Drainage and  Streetscape Improvements Project:
 
More of the same this week on Westheimer between Argonne and Dickey as crews continue installation of a Center Point electrical duct bank to run parallel to the newly installed telecommunications duct bank. This effort is the first section of work that will eventually bring overhead utility lines underground on Westheimer between Shepherd and Buffalo Speedway.

Read more...

Upper Kirby Construction: Traffic Control up Between Kirby and Argonne

Westheimer Paving, Drainage and  Streetscape Improvements Project:
 
Traffic control is finally in place on Westheimer between Kirby and Argonne following a month-long delay due to permitting issues. Now that all City concerns have been addressed, construction on the 4-month long utility relocation phase of the Westheimer Drainage and Streetscape Improvements Project can move forward.

Read more...

Upper Kirby Construction: Westheimer Utility Work to Begin This Month (more)

Westheimer Paving, Drainage and  Streetscape Improvements Project:
 
Texas Sterling Construction (TSC) was not able to begin mobilizing crews this week on Westheimer between Kirby and Shepherd but does expect to begin installing traffic control next week. Minor changes to materials detail has stalled the issuing of permits by the City of Houston. It is expected that permits will be released early next week. Please look for further updates next week as sequencing details are finalized.

Read more...

Upper Kirby Construction: Westheimer Utility Work to Begin This Month (more info)

Westheimer Paving, Drainage and  Streetscape Improvements Project:
 
Project signs have been placed indicating work would begin this week on the utility portion of the Westheimer Drainage and Streetscape Improvement Project. Unfortunately work has was not able to begin as expected as the project has met with complications in permitting at the City of Houston. Minor changes to materials detail requested by the City and more extensive bonding to assure the City that the roadway will be replaced following utility work is the reason for the delay. It appears that all concerns have been addressed at this point and we anticipate permits will be issued next week. This, now a several week delay, is not anticipated to impact the contractor's ability to complete the four month project prior to the 2013 holiday season. Please look for further updates next week as sequencing details are finalized.

Read more...

Upper Kirby Construction: Westheimer Utility Work to Begin This Month (continuing)

Westheimer Paving, Drainage and  Streetscape Improvements Project:
 
Texas Sterling Construction (TSC) had hoped to begin mobilizing crews and equipment for utility work on Westheimer between Shepherd Drive and Kirby Drive this week but have been stalled slightly due to a small change in material detail. TSC hopes to have pricing confirmed on the detail change so that work can begin next week. This delay will not significantly impact the project duration of approximately four months. Please look for further updates next week as sequencing details are finalized.

Read more...