News

Upper Kirby Construction: Westheimer Utility Relocation West of Kirby: Traffic Control in Place at Buffalo March 15

Westheimer Paving, Drainage and  Streetscape Improvements Project:
 
While crews are still completing some final stringing of utility leads east of Kirby, the majority of work is complete and lane impacts will be minimal over the next few days occurring only during daytime, off-peak hours.

The Upper Kirby District would like to sincerely thank the businesses along this stretch of Kirby for their patience and understanding as we improve this major corridor.
 
Westheimer West of Kirby

The effort to continue moving west with utility infrastructure will begin initial mobilization next week. Texas Sterling Construction will be looking to begin installing traffic control on the south side of Westheimer at Buffalo Speedway on Saturday, March 15th. 

Construction will be undertaken in 1000-foot segments and will impact the two eastbound lanes on the south side of Westheimer. Traffic will be shifted to one lane in either direction through the construction zone. Each 1000-foot segment is expected to take four to five weeks to complete. Once a given segment is completed, it will be restored with asphalt and opened prior to the next segment beginning.

The contract duration on this project is 120 days putting completion somewhere around June/July 2014. Weather permitting, roadway construction between Kirby and Shepherd should be able to begin immediately following utility completion west of Kirby.
 
CenterPoint and the telecommunications companies will follow behind duct bank construction reconnecting services underground. The duration of this reconnection work will be up to the utility providers though 45 to 90 days is typical. Traffic impact during this work is negligible. 
 
Once the utilities have been removed and the lines brought underground west of Kirby, Upper Kirby will move forward with drainage and underground infrastructure improvements followed by complete repaving of the roadway. The project will also entail the installation of a pedestrian-oriented streetscape similar to the treatment provided on the recent Kirby Drive and Buffalo Speedway projects. This work will first be completed between Shepherd and Kirby followed by an identical scope of work between Kirby and Buffalo Speedway. 
 
Roadway reconstruction is anticipated to last approximately 10 months. Drainage improvement and roadway reconstruction between Kirby and Buffalo will immediately follow and will have a similar approximate duration.
 
For more information on Upper Kirby construction and related activities or for construction related issues or concerns, please contact Travis Younkin at 713.524.8000 or This email address is being protected from spambots. You need JavaScript enabled to view it..